§ 15. Locations.  


Latest version.
  • No shelter shall be placed upon the public street or highway right-of-way until the following procedure has been accomplished and the location has been approved by the council;

    A.

    The company shall give written notice to abutting property owners at least ten (10) days prior to the date set for a public hearing and furnish them with a site plan upon their request.

    B.

    The company shall print in a newspaper of general circulation in the City of Saint Paul at least ten (10) days prior to the date set for public hearing, notice of such public hearing.

    C.

    The company shall submit to the director of public works ten (10) copies of a site plan, a description of how electrical service will be provided and any unique shelter design required to accommodate the shelter to the location, and any other information the director may require. No shelter may be placed upon the public right-of-way unless the site plan is approved by the director.

    D.

    The company shall notify all utility locaters and submit to the director proofs that such notice has been given.

    E.

    The company must obtain all building and other required permits from the city or any other agency of government as the law requires, including a permit from the proper road authority if other than the city.

    The council shall hold a public hearing with regard to the approval of all new locations. All locations and installations must conform to the zoning ordinance of the city.

(Ord. No. 17237, § 15, 5-9-85; C.F. No. 95-516, § 15, 6-7-95; C.F. No. 05-457, § 15, 6-8-05)